Chemical plant construction site with structural steel, pipe racks and a mobile crane

Design. Procure. Build.

EPC and EPCM project
management for process plants.

One team from first sketch to first batch.

We take chemical and formulation plants from concept to handover: feasibility, front-end and detailed engineering, procurement, construction management and commissioning support, with one accountable team.

Project Delivery Scope

The phases and disciplines a plant project runs through, from concept to handover.

EPC
EPCM
Feasibility & business case
01
Site & layout planning
02
Front-end design (FEED)
03
Detailed design & 3D coordination
04
Sourcing & vendor control
05
Site construction oversight
06
07
Process & piping design
08
Structures & buildings
09
Power, instruments & controls
10
Utilities, ventilation & fire safety
11
Hazard & risk studies
12
Start-up & performance proof
Project Mapping

Project Stages & Deliverables

What each stage of a plant project delivers, and the decisions it locks in.

Service Area
What We Deliver
Where It Applies
Engineering Detail

Feasibility and concept design

Planning
Process concept
Capacity and site options
Order-of-magnitude cost estimate
New plants and major expansions.
⚙️

Scope & Configuration

Test whether the project works technically and commercially before committing engineering effort.

Design Basis

Product slate, capacity, raw materials, site constraints and regulatory needs.

📐

Method & Approach

Develop the process concept, a first mass balance and the utility needs, compare site and technology options, and prepare an estimate with a stated accuracy class.

Risk & Quality Controls

Estimate accuracy is stated, and assumptions are listed so they can be tested later.

Site master planning and layout

Planning
Plot plan
Zoning and traffic flow
Expansion provision
New sites and additions to existing sites.
⚙️

Scope & Configuration

Placement of process, utilities, storage, effluent treatment and offices with safe separation and room to expand.

Design Basis

Site boundaries, statutory setbacks, material flows and hazard separation.

📐

Method & Approach

Map how people and goods move, zone the site by hazard and function, set separation distances, and reserve space for expansion.

Risk & Quality Controls

The layout reflects fire, explosion and environmental constraints from the start.

FEED and basic engineering

Engineering
Basis of design
PFDs and heat and material balances
Equipment list and P&ID development
Plants of all sizes.
⚙️

Scope & Configuration

Define the process, equipment and cost to a level that can be tendered.

Design Basis

The process design package, design codes and owner requirements.

📐

Method & Approach

Fix the design basis, develop PFDs and P&IDs, size major equipment, and prepare datasheets and a cost estimate suitable for procurement.

Risk & Quality Controls

Design reviews and a safety study are done while change is still inexpensive.

Detailed engineering and 3D modelling

Engineering
Detailed drawings
Piping isometrics and material take-offs
3D model with clash checks
Plants moving to construction.
⚙️

Scope & Configuration

Engineering across process, piping, civil, structural, electrical and instrumentation disciplines.

Design Basis

Approved basic engineering and vendor data.

📐

Method & Approach

Develop each discipline’s drawings and specifications in a coordinated 3D model, check interfaces and clashes, and issue construction packages.

Risk & Quality Controls

Interdisciplinary clash and constructability reviews are completed before issue for construction.

Revamping existing plants with laser scanning

Engineering
As-built point cloud
Revamp design
Tie-in and shutdown plan
Existing plants being modified or expanded.
⚙️

Scope & Configuration

Capture the plant as it really is, then design modifications that fit.

Design Basis

Scan data, existing drawings and available shutdown windows.

📐

Method & Approach

Capture the existing plant by 3D laser scanning, build a model from the point cloud, design the modification in that model, and plan tie-ins to fit the shutdown.

Risk & Quality Controls

Clashes with existing pipework are found on screen rather than on site.

Procurement and vendor management

Procurement & build
Vendor prequalification
Bid comparison
Inspection and expediting
Equipment, instruments and bulk materials.
⚙️

Scope & Configuration

Buy the right equipment at an acceptable cost and delivery.

Design Basis

Approved datasheets and the long-lead items on the project schedule.

📐

Method & Approach

Prequalify vendors, run enquiries against datasheets, compare technical and commercial bids, and follow fabrication through inspection and expediting.

Risk & Quality Controls

Stage-wise inspection of fabricated equipment and tested panels before shipment.

Construction management

Procurement & build
Construction plan
Quality and safety supervision
Progress reporting
Plants under construction.
⚙️

Scope & Configuration

Supervise contractors against drawings, quality plans and safety rules.

Design Basis

Issued-for-construction drawings and the contract scope.

📐

Method & Approach

Manage contractors and interfaces, supervise installation quality and site safety, track progress and changes, and certify work done.

Risk & Quality Controls

Permit-to-work, inspection and test plans, and change control are enforced on site.

Commissioning and start-up support

Start-up
Pre-commissioning and commissioning plan
Performance test
Handover documents
Newly built or modified plants.
⚙️

Scope & Configuration

Bring the plant into service safely and prove that it meets the design basis.

Design Basis

Mechanical completion records and performance guarantees.

📐

Method & Approach

Move from mechanical completion through pre-commissioning and commissioning to start-up, verify performance against the guarantees, and hand over documentation and training.

Risk & Quality Controls

A pre-startup safety review gates the first introduction of process material.

How a plant project runs

Project Delivery

From Concept to Handover

Each stage locks in decisions that become expensive to change later, which is why the early stages get the most scrutiny.

Scroll to follow the project
Stainless steel vessels and blue pipework on multi-level platforms in a process plant
01 Concept

Feasibility & Concept

Define the process concept, capacity, site options and a first estimate, and decide whether the project should proceed.

Speak With Our Engineers
Laser scanner on a tripod between rows of pipework in a process plant
02 FEED

FEED & Basic Engineering

Fix the basis of design, develop PFDs and P&IDs, size major equipment and produce an estimate that can support a decision to invest.

Speak With Our Engineers
Stainless steel vessels and blue pipework on multi-level platforms in a process plant
03 Engineering

Detailed Engineering

Produce coordinated drawings and specifications across all disciplines in a 3D model, and issue construction packages.

Speak With Our Engineers
Skid-mounted pump and valve station with stainless steel pipework in an industrial hall
04 Procurement

Procurement

Prequalify vendors, compare bids, place orders, and follow fabrication through inspection and expediting.

Speak With Our Engineers
Chemical plant construction site with structural steel, pipe racks and a mobile crane
05 Construction

Construction Management

Supervise contractors for quality and safety, control changes and progress, and verify work against the drawings.

Speak With Our Engineers
Jacketed stainless steel batch reactor with a relief line and catch tank in a reactor bay
06 Handover

Commissioning & Handover

Take the plant from mechanical completion to start-up, verify performance, and hand over documents and training.

Speak With Our Engineers
Let's Collaborate

Planning a new plant or an expansion?

Tell us about the product, capacity and site, and we will outline the feasibility work and the engineering scope.

Discuss Your Project
Knowledge Base

Plant Engineering Knowledge Base

Scale-up, pilot plant, reactor material and facility guides from our technical team.

FAQ

Frequently asked questions

Straight answers to the questions we hear most often.

What is the difference between EPC and EPCM?

In EPC, one contractor is responsible for engineering, procurement and construction, usually for a fixed price, and carries most of the delivery risk. In EPCM, the contractor manages engineering, procurement and construction on the owner’s behalf while the owner contracts the suppliers and builders directly, so the owner keeps more control and more of the cost risk.

What is FEED and why does it matter?

Front-end engineering design (FEED) defines the process, major equipment, layout and cost to a level that can be tendered. It fixes the scope before large sums are committed, so it is where changes are cheapest and where cost estimates become reliable.

How accurate is a project cost estimate?

It depends on how far the design has progressed. Estimate classes, such as the AACE classification, run from early order-of-magnitude estimates with wide ranges to definitive estimates based on detailed engineering, and each class states its expected accuracy range. An estimate should always be quoted with its class and the assumptions behind it.

When is 3D laser scanning used?

It is used on existing plants where drawings are missing or out of date. A scan captures the plant as a point cloud, from which a model is built so that a modification can be designed and checked for clashes before work begins on site, which helps shorten shutdowns.

What is the difference between mechanical completion, commissioning and start-up?

Mechanical completion means construction is finished and checked against the drawings. Commissioning tests systems and utilities, first without and then with process materials. Start-up is the first production run, after which performance is tested against the agreed guarantees.

Can you work on an existing plant while it keeps running?

Yes. Work on live plants relies on accurate as-built data, careful planning of tie-ins and shutdown windows, and strict permit-to-work control, so modifications are prepared offline and the time connected to the live plant is kept short.

Contact Details

Reach us directly.

Prefer a direct line? Reach our formulation team through any channel below — we typically respond within one business day.

Message on WhatsApp