Water Treatment

Wastewater Treatment Design: Flow, Load, Treatability

Wastewater treatment design subject — round clarifier, rectangular aeration basins and a bridge walkway at a wastewater treatment plant at night | Global Formulation
A clarifier and aeration basins at a wastewater treatment plant: the units whose sizes follow the design flows and the design loads.

A project team asks a designer for a treatment plant and cannot say how much wastewater there is, how strong it is or how it varies. Wastewater treatment design turns the design flow, the design load, the treatability of the wastewater and the discharge standard into a process route with sized units. This guide covers the design basis behind that work, for industrial and municipal-type wastewater. It explains how design flows and loads are defined, how treatability evidence is gathered and how those inputs choose the treatment steps. It draws on the US EPA's municipal wastewater primer, the 2014 Ten States Standards and Directive 91/271/EEC, and every figure is labelled by source and region. The approach reflects the water and wastewater engineering work that Global Formulation provides to plant owners.

Wastewater Treatment Design Basis: The Four Values to Fix

Every sizing decision in a treatment plant rests on a short list of values that someone must fix and record. The design basis is the document that holds them, with the source of each. Four groups matter: the design flows, the design loads, the treatability evidence and the discharge or reuse standard. The table shows what each group fixes and where the evidence comes from.

InputWhat to fixWhere the evidence comes from
Design flowsAverage, maximum day, peak hour and peak instantaneous flow for a stated design yearFlow records or measurements for an existing site; water-use data and a per-capita basis for a new one
Design loadsMass per day of BOD5, suspended solids and any named pollutant, in the same forms as flowSampling stream by stream across the production cycle; a named convention for domestic flows
TreatabilityEvidence that the chosen route works on this wastewaterBench, settling or pilot tests on real samples
StandardThe rule or permit, the receiving medium and the point where compliance is measuredThe regulator, labelled by jurisdiction

Our guide to effluent treatment plant design covers the factory-side detail, including sampling, equalisation volumes and layout. This guide stays on how the values are defined and tested, because those definitions decide whether two quotations are comparable. Where the discharge standard is concerned, the jurisdictions are set out in that guide and are not repeated here.

Figure 1 shows the order in which the values are fixed. The standard is named before the treatability tests, because it sets how far the tests must look. A change in any input sends the work back before the units are sized.

Illustrative sequence from design inputs to sized units Six numbered steps in two rows. The top row runs from fixing the design flows, through fixing the design loads, to naming the discharge standard. An arrow leads down to the second row, which runs from testing treatability, through selecting the treatment steps, to sizing the units. Dashed labels read measured where a site exists under the first step, name the convention under the second step and evidence, not a table under the treatability step. A note says that a change in any input sends the work back before the units are sized. The figure is a generic illustration. 1 Fix design flowsFour forms, design year 2 Fix design loadsKilograms per day 3 Name the standardRule, medium, compliance 4 Test treatabilityBench or pilot, real samples 5 Select the stepsPreliminary to tertiary 6 Size the unitsFlow, load, test results Measured where a site exists Name the convention Evidence, not a table A change in any input sends the work back before the units are sized.
Figure 1. Illustrative sequence from design inputs to sized units. The steps are generic and do not describe any particular plant.

Design Flow: Average, Maximum Day, Peak Hour and Peak Instantaneous

Design flow is not one number. The Recommended Standards for Wastewater Facilities, known as the Ten States Standards, come from ten US states and the province of Ontario. Their 2014 edition requires the design year's flows to be identified in four forms and used as the basis of design. The table gives the definitions and what each form is used for.

Design flowDefinition in the Ten States StandardsWhat it is used for
AverageThe average of the daily volumes over a continuous 12 months; for facilities with a critical seasonal high loading, such as industrial facilities, the average over the seasonal periodThe base figure for volumes, and the seasonal average for a seasonal industrial site
Maximum dayThe largest volume received in a continuous 24 hoursDaily throughput, paired with the maximum day BOD5 when removal is tested
Peak hourlyThe largest volume received in one hourThe hydraulic peak on unit processes, pumping, piping and settling tanks
Peak instantaneousThe instantaneous maximum flow rate receivedThe highest rate a structure must pass; fine screens must treat it with one unit out of service

How the flows are established depends on the site. For an existing system the Standards require projections from actual flow data to the extent possible. For a new system serving domestic users they base sizing on 100 gallons, or 380 litres, per person per day. They add the flow from industrial plants and major institutional and commercial facilities unless water-use data or another justification gives a better estimate.

The ratio of peak to average decides whether the plant needs a buffer. In their wet weather provisions the Standards state that flow equalisation shall be considered when the ratio of design peak hourly flow to design average flow is 3:1 or more. A batch plant discharges in pulses, so an industrial flow does not follow a per-capita pattern. Measured flow over a production cycle replaces any formula for such sites. Utility streams such as cooling tower blowdown count as flow too, and our guide to cooling tower water treatment covers their chemistry. Our water flow mapping and site balance work is how measured flow is obtained.

Wastewater flow in a concrete channel — water falling over a drop between handrailed walls with a grating walkway | Global Formulation
Wastewater in a concrete channel with a drop structure: where a site exists, design flows come from measurement and not from assumption.

Design Load: BOD5, Per-Capita Bases and Population Equivalents

Load is the mass of each pollutant that arrives per day, and the design carries it in the same forms as flow. The Ten States Standards define the design average, maximum day and peak hourly BOD5 as weights per day. For domestic wastewater they also set a per-capita basis, while European Union law uses a different unit. The comparison below shows why the convention must be named.

ConventionBasisSource and region
Per-capita design loadAt least 0.17 lb (0.08 kg) of BOD5 and 0.20 lb (0.09 kg) of suspended solids per person per day, unless information justifies another design. For nitrification, the Standards give 0.036 lb (0.016 kg) of TKN per person per dayTen States Standards, 2014 edition, for domestic wastewater; ten US states and Ontario
Population equivalentOne population equivalent is the organic biodegradable load with a five-day BOD of 60 g of oxygen per dayDirective 91/271/EEC, European Union

The directive has since been recast. Directive (EU) 2024/3019 entered into force on 1 January 2025, so the current text governs any definition that applies to a European project. The two conventions give different answers for the same wastewater, as the invented example below shows. It describes no real plant and uses plain arithmetic.

QuantityWorkingResult
Daily BOD5 load120 m³/day × 1,500 g/m³ (1 mg/L equals 1 g/m³)180,000 g/day, or 180 kg BOD5/day
In population equivalents180 kg ÷ 0.060 kg per p.e.3,000 p.e.
In per-capita domestic loads180 kg ÷ 0.08 kg per person2,250 persons' worth of domestic load

The same wastewater is 3,000 population equivalents or 2,250 persons' worth, depending on the convention. State the load in kilograms per day first and name the convention beside any equivalent. Industrial loads are measured stream by stream, and the per-capita bases apply to domestic wastewater only.

Treatability: The Evidence That a Route Works on This Wastewater

A treatment route chosen from a table of technologies is a hypothesis until it is tested on the real wastewater. Treatability work tests that hypothesis at bench or pilot scale before equipment is ordered. The Ten States Standards recommend pilot testing to verify performance predictions, particularly when significant amounts of industrial wastes are present. The EPA primer explains why: toxic compounds impair the activated sludge process unless they are controlled at source.

QuestionTestDesign decision it settles
How much coagulant does the chemical step need?A jar test on the real wastewaterThe coagulant dose and the chemistry of the coagulation stage
Will the solids settle at the planned loading?A settling test; the Ten States Standards require one where a pilot study is warranted by unusual waste characteristics, treatment requirements or loadings beyond their limitsThe clarifier overflow rate and solids loading
Does the biology tolerate the wastewater at the planned load?A bench or pilot biological test on the real wastewater over a representative periodWhether biological treatment suits the stream, or whether a toxic stream must be separated first
Which pollutants pass through the chosen route?Analysis of the treated test effluent against the standardWhether a further step is needed beyond secondary treatment

The samples must represent the variation described in the flow and load sections. A test on a blended average hides the stream that causes the trouble, so the tests run stream by stream and on the blend. Reference texts such as Metcalf and Eddy's Wastewater Engineering: Treatment and Resource Recovery and the Water Environment Federation's Manual of Practice 8 hold the design equations that the tests verify. The chemistry of the coagulants and flocculants themselves belongs to our water treatment vertical.

Treatability test — six beakers on a laboratory bench showing wastewater clearing as solids settle | Global Formulation
A row of beakers holding the same wastewater at different stages of settling: bench tests on real samples are the first evidence of treatability.

Wastewater Treatment Steps: Primary, Secondary and Tertiary Treatment

The steps in a wastewater treatment plant follow a standard order that the design inputs then adjust. The EPA's primer describes preliminary, primary and secondary treatment, and then treatment beyond secondary, which it calls advanced treatment. This guide uses tertiary treatment for that last stage. The table gives each step, what it does and the design input that decides whether it is needed.

StepWhat it does, as the EPA primer describes itDesign input that decides it
PreliminaryScreens remove large floating objects such as rags, cans, bottles and sticks; grit chambers remove sand and small stonesPeak flow, and the solids and grit load
PrimarySedimentation removes coarse solids, which leave as primary sludgeFlow and settleability
SecondaryBiological treatment, by attached-growth or suspended-growth processes, removes up to 90 percent of the organic matterOrganic load and treatability
Tertiary, or advancedTreatment beyond secondary removes nitrogen and phosphorus, and uses adsorption, flocculation and precipitation, membranes, ion exchange or reverse osmosisThe discharge or reuse standard

In the United States the Clean Water Act requires municipal plants to meet a minimum of secondary treatment. The 2004 primer reports that over 30 percent of plants provided more than secondary treatment. The standard therefore decides how far the train extends, which is why it is fixed before the steps are chosen.

Industrial plants add steps for what a municipal plant rarely sees, and our guide to effluent treatment plant design maps pollutants to technologies. Every step also leaves residuals, which the primer says must be reused, burned, buried or disposed of in a way that does not harm the environment. The sludge route is therefore a design input and not an afterthought.

What Goes Wrong When the Design Inputs Are Weak

Wastewater treatment design fails in a recognisable way: the plant is built to a number that nobody measured or tested. The causes sit in the definitions, the evidence and the order of decisions. Each failure has a consequence in operation and a prevention in the brief. The table lists the common ones.

What goes wrongConsequenceHow to prevent it
Flow taken from assumptions at an existing siteThe plant is sized for a flow it never receivesProject from actual flow data, as the Ten States Standards require where possible
Only the average flow is statedHydraulic peaks reach the units, pumps, pipes and settling tanks unplannedState all four design flows and check the peak-to-average ratio against the 3:1 trigger for equalisation
Initial low flows ignoredFreezing, septicity, flow measurement problems and solids dropout appear in the early yearsEvaluate the initial low flow as the Standards require
Per-capita values applied to an industrial dischargeThe industrial load is missed or mis-sizedMeasure industrial flows and loads and add them to the domestic basis separately
The load convention is not namedThe same wastewater is quoted at different capacities and bids cannot be comparedState kilograms per day first, then name the convention for any equivalent
Treatability skipped for an industrial wastewaterToxic compounds impair the biological stepRun the biological and settling tests on real samples before the route is fixed
The standard is fixed after the steps are chosenThe train stops at secondary treatment when the standard needs more, so a later upgrade followsName the rule, the medium and the compliance point at the start

Most of these failures are specification failures. A designer can only work to a flow, a load and a standard that someone stated and evidenced.

Commissioning Wastewater Treatment Design: An Owner's Checklist

The owner's brief decides whether a design is built on evidence or on assumption. Eight items cover it. Work through them in order, because each one constrains the next. The result is a brief that designers can price and an engineer can check.

  1. State the design year and the horizon — the year the flows and loads apply to, and any planned expansion.
  2. Supply the four design flows — average, maximum day, peak hour and peak instantaneous, from measurement where the site exists.
  3. Supply the design loads — kilograms per day for each named pollutant and stream, with the sampling dates and methods.
  4. Name the load convention — per-capita basis or population equivalent, with the source of the figure.
  5. Commission treatability work — jar, settling and biological tests on real samples, covering the variation in the wastewater.
  6. Name the standard — the rule or permit, the receiving medium, the jurisdiction and the point of compliance.
  7. Fix the sludge and residuals route — how each step's residuals leave the site.
  8. Ask for the design basis document — every input above with its source, signed off before sizing begins.

On delivery, check that each design flow and load has a source, that the treatability report states the samples and the method, and that the standard is named. To test the work, recompute one load as flow multiplied by concentration and compare the peak-to-average ratio with the plant's equalisation. The checklist is the brief to bring for wastewater treatment plant design. Our water and wastewater engineering service sets the basis of design first, with water audits, bench and pilot testing of options and treatment-route selection. Factory effluent is handled under our effluent treatment plant engineering service.

Frequently Asked Questions

What is wastewater treatment design?

Wastewater treatment design is the engineering work that turns a wastewater's flow, load, treatability and discharge standard into a treatment process with sized units. It starts with a design basis that records each input and its source.

The process route, the unit sizes and the layout follow from that basis. A plant designed on unmeasured or untested inputs fails however well its equipment is built.

What are the design flows in a wastewater treatment plant?

The Ten States Standards, 2014 edition, require four forms of flow for the design year. They are the design average flow, the design maximum day flow, the design peak hourly flow and the design peak instantaneous flow.

Each form checks a different part of the plant. For an existing system the Standards require projections from actual flow data to the extent possible.

How is the design load of a wastewater treatment plant calculated?

Load is flow multiplied by concentration, expressed as a mass per day for each pollutant. Industrial loads come from sampling each stream across the production cycle.

For domestic wastewater the Ten States Standards use at least 0.08 kg of BOD5 per person per day unless information justifies another design. State the load in kilograms per day first and name any convention beside it.

What is a population equivalent?

A population equivalent is a unit of organic load. Directive 91/271/EEC defines one population equivalent as the organic biodegradable load with a five-day BOD of 60 g of oxygen per day.

Directive (EU) 2024/3019 recast the directive and entered into force on 1 January 2025, so check the current text. A different convention, such as 0.08 kg of BOD5 per person per day, gives a different count for the same wastewater.

What is a treatability study?

A treatability study tests a proposed treatment route on the real wastewater at bench or pilot scale before equipment is ordered. Typical tests include a jar test for coagulant dose, a settling test and a biological test over a representative period.

The Ten States Standards recommend pilot testing to verify performance predictions, particularly when significant amounts of industrial wastes are present. The samples must cover the variation in the wastewater.

What are the steps in a wastewater treatment plant?

The EPA primer describes preliminary treatment, primary treatment and secondary treatment, followed by advanced treatment where the standard needs it. Screens and grit chambers come first, sedimentation next and biological treatment third.

Each step leaves residuals that must be reused or disposed of. The design inputs decide which steps a given plant needs.

What is the difference between primary, secondary and tertiary treatment?

Primary treatment removes coarse solids by sedimentation. Secondary treatment uses biological processes to remove up to 90 percent of the organic matter, according to the EPA primer.

Tertiary treatment goes beyond secondary, to remove nitrogen and phosphorus or to polish the water for reuse. The EPA primer calls this stage advanced treatment.

How does the discharge standard affect wastewater treatment design?

The standard sets how far the treatment train must go. In the United States the Clean Water Act sets secondary treatment as the minimum for municipal plants. The EPA's 2004 primer reports that over 30 percent of plants provide more.

The rules differ by jurisdiction, industry and receiving medium, so name the one that governs the site at the start. Our effluent treatment plant design guide sets out examples for the United States, India and the European Union.

Need a Treatment Design Basis You Can Rely On?

Global Formulation provides effluent and wastewater treatment plant design, treatment-route selection, design-basis and treatability work, and water audits for process industries.

Discuss a Water Project
AK

Absar Khan

Founder & Lead Consultant, Global Formulation

Absar Khan is a senior industrial consultant with cross-disciplinary expertise spanning chemical process engineering, reaction engineering, and industrial formulation. He founded Global Formulation to provide accessible, expert-led process development and scale-up services to manufacturers and entrepreneurs in the chemical industry. Connect with him on LinkedIn.

Message on WhatsApp